Proposed Projects
Paving of SR446 ( from US 224 south to SR 14) –
this is a
State Department of Transportation
administered project scheduled for the summer of 2010. Project is
funded entirely from ARRA stimulus funds
Northeast
Stormwater Management Project –Phase V –
Project is the fifth and final phase and shall be located near parts
of Neff Dr., Callahan Dr., Winona Dr..
Project is scheduled to commence after
July 1, 2010. Total project cost is estimated at $ 628,000 of which
$ 433,320 is in the form of a grant to the City of Canfield from the
Ohio Public works Commission.
Fairground Blvd. and Hood Drive Enhancement Project –
Project includes the placement of sidewalks along the south side of
Fairground Blvd. from SR 46 to the Main entrance to the Fairgrounds,
and along the Westside of Hood drive from Indian Lake Blvd. south to
Fairground Blvd. Project is funded in part by a grant from the Ohio
Department of Transportation covering 80% of the total project cost.
Said project is slated to commence in late 2011. Estimated project
cost $ 316,000 of which $ 252,800 (80%) is in the form of a ODOT
Enhancement grant and $63,200 (20%) is the local share of the
project.
ARRA Funded
projects: City of
Canfield
Herbert Road &
Fairground Blvd.:
Projects Funded
with American Recovery and Reinvestment Act Funding.
100% funding from
ARRA
City of Canfield
local share - $ 0.00
Estimated Project
Cost $ 400,000
Fairground Blvd.
– completed Friday May 14, 2010
Herebert Road –
Base course completed Thursday May 13, 2010
Top course scheduled completion date Friday May 28, 2010

|